During the final plan review, Program risks are addressed using ROAM. What do the letters in ROAM represent?
During the final plan review, Program risks are addressed using ROAM. What do the letters in ROAM represent? A) Owned, Mitigated, Active,Resolved B) Owned, Mitigated, Resolved,Accepted C) Resolved, Assigned,Migrated, Owned D) Resolved. Owned. Approved, Mitigated --- This is a tricky questions, The correct Answer is B as Wrong Answer D is the only one having the words in right order. ROAM is described in the PI Planning Section Resolved – The teams agree that the risk is no longer a concern. Owned – Someone on the train takes ownership of the risk since it cannot be resolved during PI planning. Accepted – Some risks are just facts or potential problems that must be understood and accepted. Mitigated – Teams identify a plan to reduce the impact of the risk. © Scaled Agile, Inc. Include this copyright notice with the copied content.