During the final plan review, Program risks are addressed using ROAM. What do the letters in ROAM represent?

During the final plan review, Program risks are addressed using ROAM. What do the letters in ROAM represent?


A) Owned, Mitigated, Active,Resolved
B)  Owned, Mitigated, Resolved,Accepted
C) Resolved, Assigned,Migrated, Owned
D) Resolved. Owned. Approved, Mitigated


---

This is a tricky questions, 

The correct Answer is B

as  Wrong Answer D is the only one having the words in right order. 

ROAM is described in the PI Planning Section



Resolved – The teams agree that the risk is no longer a concern. Owned – Someone on the train takes ownership of the risk since it cannot be resolved during PI planning. Accepted – Some risks are just facts or potential problems that must be understood and accepted. Mitigated – Teams identify a plan to reduce the impact of the risk.

© Scaled Agile, Inc.
Include this copyright notice with the copied content.



Kommentare

  1. FairPlay Casino: The Most Fair Casino Online!
    FairPlay is a free-to-play, slot-machine games developer with 11bet a history that includes 퍼스트카지노 offering slot machine games to slot players around the 메리트카지노 world. Read More.

    AntwortenLöschen

Kommentar veröffentlichen

Beliebte Posts aus diesem Blog

SoCraTes Day Franken 2019

An Enterprise has just adopted the SAFe Implementation Roadmap and is in the process of training executives, managers, and leaders. What is their next step?